How Many Constraints Are There In Primavera P6?

 


In project management, real-world limitations are unavoidable—and Primavera P6 scheduling software helps project planners account for them through constraints. Constraints in P6 are conditions that restrict the scheduling of activities, either by setting specific dates or by dictating when activities can or cannot occur. These are crucial tools for aligning your project schedule with external dependencies, resource availability, or stakeholder expectations.

Types of Constraints in Primavera P6

P6 allows you to apply up to two constraints per activity through the Status detail window or directly via the Gantt chart. These constraints fall into two primary categories: hard constraints and soft constraints.

Hard Constraints:

  • Mandatory Start: Forces an activity to begin on a specific date, regardless of logic.
  • Mandatory Finish: Forces an activity to end on a specific date, again ignoring network dependencies.

These constraints override network logic, meaning they can significantly impact the flow and flexibility of your schedule.

Soft Constraints:

  • Start On: Requires the activity to start on a specific date.
  • Start On or Before / After: Limits when an activity can start, either on or before or on or after a specified date.
  • Finish On: Requires the activity to finish on a specific date.
  • Finish On or Before / After: Defines time boundaries for when an activity can finish.

Soft constraints influence the scheduling process without entirely blocking logic-based changes. They primarily affect early or late start/finish dates and may distort float, which can give misleading signals about schedule flexibility.

Additional Constraint:

  • As Late As Possible (ALAP): Schedules an activity as late as it can start without affecting successor activities, this is useful when resources are limited or when delaying the activity has strategic advantages.

Why Use Constraints?

Constraints serve multiple purposes in Primavera P6:

  • Reflect real-world commitments, such as regulatory approvals or vendor delivery dates.
  • Prevent scheduling errors or unrealistic start/finish dates.
  • Improve schedule accuracy and communication with stakeholders.

However, it’s important not to overuse constraints. Excessive or conflicting constraints can make a schedule rigid and less responsive to changes, ultimately defeating the purpose of dynamic scheduling.

Need Expert Guidance or Hands-On Training With Primavera P6?

Global PM offers comprehensive Primavera P6 scheduling software training—from beginner to advanced levels—across the U.S., including Houston, New Orleans, NYC, Orlando, Ft. Lauderdale, and Atlanta. Choose from live virtual sessions or private in-person courses tailored to your team. Contact us today!

 

Comments

Popular posts from this blog

How to Do Scheduling in Primavera P6

What is the Work Breakdown Structure in Primavera P6?