How to Do Scheduling in Primavera P6
Proper scheduling in
Primavera P6 ensures efficient resource allocation and timely project
completion. Here's a step-by-step guide on how to enable and use
auto-scheduling in Primavera
P6 scheduling software:
1.
Start
with a Simple Project Plan:
Make sure your project plan is created and open in Primavera P6.
2.
Check
Activity Scheduling: Identify
any activities that are scheduled to start before their predecessors. For
example, "Define resource list from kickoff meeting report" should
start after "Project kickoff meeting."
3.
Define
Dependencies: Define
dependencies between activities. You can read articles or guides on adding
dependencies in Primavera P6 if needed.
4.
Access
the Schedule Dialog Box: On
the P6 ribbon, go to Tools > Schedule.
5.
Open
Schedule Options: In the
Schedule dialog box that appears, select Options....
6.
Enable
Auto-Scheduling: On the
General tab, check the box for Schedule automatically when a change affects
dates.
7.
Commit
Changes: Click Close to
save the changes to Schedule Options. Back in the Schedule dialog box, click
the green Schedule button.
8.
Review
Adjustments: Check your list
of activities. The start date for "Define resource list from kickoff
meeting report" should now be adjusted to fall after "Project kickoff
meeting."
9.
Add New
Activities and Dependencies:
As you add new activities and dependencies to your project, dates will
automatically shift to reflect an accurate project plan.
10. Monitor and Update: Regularly monitor your project plan and make
updates as necessary to ensure accurate scheduling.
By following these
steps, project managers can effectively schedule and control projects using
Primavera P6. If you are facing any difficulties in handling projects with
Primavera P6 scheduling software, you can sign in for a 2-day basic to advanced
Primavera training at Global PM. Contact us
now to learn more.